Lafayette Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct Lafayette Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: April 2016
Projected Completion Date:
April 2017
Completion Date:
June 2017
Procurement
Start Date: June 2017
Projected Completion Date:
March 2018
Completion
Date:
May 2018
Construction
Start Date: May 2018
Projected Completion Date:
August 2019
Completion Date: July 2019
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Lafayette Playground, Brooklyn
Benson Avenue, Bay 43rd Street, Stillwell Avenue
Community Board: 13
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 01/17/2025