Project Timeline
Design
Assigned & Start Date: March 2016
Projected Completion Date:
March 2017
Completion Date:
April 2017
Procurement
Start Date: April 2017
Projected Completion Date:
December 2017
Completion
Date:
August 2017
Construction
Start Date: September 2017
Projected Completion Date:
September 2018
Completion Date: October 2018