Ogden Plimpton Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct Ogden Plimpton Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: March 2016
Projected Completion Date:
March 2017
Completion Date:
April 2017
Procurement
Start Date: April 2017
Projected Completion Date:
January 2018
Completion
Date:
February 2018
Construction
Start Date: March 2018
Projected Completion Date:
March 2019
Completion Date: December 2018
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
- Mayoral
Location
Ogden Plimpton Playground, Bronx
Plimpton Avenue between West 170th Street and Edward L Grant Highway.
Community Board: 04
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project
Last updated: 01/17/2025