Walton Park Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the playground at Walton Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: April 2016
Projected Completion Date:
March 2017
Completion Date:
April 2017
Procurement
Start Date: April 2017
Projected Completion Date:
December 2017
Completion
Date:
January 2018
Construction
Start Date: February 2018
Projected Completion Date:
February 2019
Completion Date: February 2019
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Location
Walton Park, Bronx
East 181st Street and Walton Avenue
Community Board: 05
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project
Last updated: 11/22/2024