Coney Island Greenstreets and Green Infrastructure Construction
-
100% complete
-
100% complete
-
100% complete
This project will construct green infrastructure to capture storm water at Greenstreets at various locations near Coney Island Beach and Boardwalk.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: February 2015
Projected Completion Date:
February 2016
Completion Date:
December 2017
Procurement
Start Date: December 2017
Projected Completion Date:
August 2018
Completion
Date:
August 2019
Construction
Start Date: September 2019
Projected Completion Date:
September 2020
Completion Date: November 2020
Understand how we build parks.
Funding
Funding Sources:
- Federal
- Mayoral
Location
Between Brighton 1st Street, Neptune Avenue, West End Avenue, and the Coney Island Boardwalk
Project Staff
Contact NYC Parks about this projectLast updated: 11/22/2024