Butterfly Gardens Pavement Reconstruction and Planted Area Expansion

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Butterfly Gardens including new pavements, fencing, benches, and trash receptacles and expanded planted areas.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2015
Projected Completion Date: June 2016
Completion Date: July 2016

Procurement

Start Date: July 2016
Projected Completion Date: March 2017
Completion Date: August 2017

Construction

Start Date: September 2017
Projected Completion Date: September 2018
Completion Date: September 2018

Understand how we build parks.

Funding

Total Funding: $637,000
Funding Sources:
  • Borough President
  • Mayoral

Location

Butterfly Gardens, Brooklyn
7th Avenue and 18th Street
Community Board: 07

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 01/17/2025