West Bronx Recreation Center AC Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the air conditioning system for the gymnasium at West Bronx Recreation Center.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: July 2015
Projected Completion Date:
June 2016
Completion Date:
February 2017
Procurement
Start Date: February 2017
Projected Completion Date:
November 2017
Completion
Date:
July 2018
Construction
Start Date: October 2018
Projected Completion Date:
October 2019
Completion Date: January 2020