Patterson Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the playground and basketball courts at Patterson Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2015
Projected Completion Date: October 2017
Completion Date: March 2018

Procurement

Start Date: March 2018
Projected Completion Date: December 2018
Completion Date: February 2019

Construction

Start Date: June 2019
Projected Completion Date: June 2020
Completion Date: July 2020

Understand how we build parks.

Funding

Total Funding: $3,689,000
Funding Sources:
  • City Council
  • Mayoral

Location

Patterson Playground, Bronx
East 145th Street, Morris and Bronx Avenues.
Community Board: 01

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 10/11/2024