Patterson Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the playground and basketball courts at Patterson Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: September 2015
Projected Completion Date:
October 2017
Completion Date:
March 2018
Procurement
Start Date: March 2018
Projected Completion Date:
December 2018
Completion
Date:
February 2019
Construction
Start Date: June 2019
Projected Completion Date:
June 2020
Completion Date: July 2020
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Location
Patterson Playground, Bronx
East 145th Street, Morris and Bronx Avenues.
Community Board: 01
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project
Last updated: 01/17/2025