Corlears Hook Park Dog Run Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the dog run at Corlears Hook Park, adding stable ground surface, water features and dog waste containers, and replacing fencing.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2017
Projected Completion Date: October 2018
Completion Date: November 2018

Procurement

Start Date: November 2018
Projected Completion Date: August 2019
Completion Date: October 2019

Construction

Start Date: October 2019
Projected Completion Date: October 2020
Completion Date: October 2020

Understand how we build parks.

Funding

Total Funding: $851,000
Funding Sources:
  • City Council
  • Mayoral

Location

Corlears Hook Park, Manhattan
Cherry Street, Jackson Street, FDR Drive
Community Board: 03

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 01/17/2025