John Jay Park Sitting Area Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the sitting area at John Jay Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2018
Projected Completion Date: March 2019
Completion Date: June 2019

Procurement

Start Date: June 2019
Projected Completion Date: March 2020
Completion Date: April 2021

Construction

Start Date: September 2021
Projected Completion Date: September 2022
Completion Date: May 2022

Understand how we build parks.

Funding

Total Funding: $632,000
Funding Source: City Council

Location

John Jay Park, Manhattan
FDR Drive between East 76th Street and East 78th Street
Community Board: 08

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/22/2024