Thomas Jefferson Park Irrigation Installation
-
100% complete
-
100% complete
-
100% complete
This project will install new irrigation and paths at Thomas Jefferson Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: February 2016
Projected Completion Date:
February 2017
Completion Date:
June 2018
Procurement
Start Date: June 2018
Projected Completion Date:
March 2019
Completion
Date:
June 2019
Construction
Start Date: July 2019
Projected Completion Date:
July 2020
Completion Date: September 2019
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Location
Thomas Jefferson Park, Manhattan
First Avenue between East 111th Street and East 114th Street
Community Board: 11
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 11/22/2024