Poor Richard's Playground Entry Path Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the 2nd Avenue entry path to Poor Richard's Playground with new benches, game tables, lighting, fencing, and landscaping.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: January 2016
Projected Completion Date:
January 2017
Completion Date:
April 2017
Procurement
Start Date: April 2017
Projected Completion Date:
December 2017
Completion
Date:
January 2018
Construction
Start Date: August 2018
Projected Completion Date:
August 2019
Completion Date: August 2019
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
Location
Poor Richard's Playground, Manhattan
East 108th Street at 2nd Avenue
Community Board: 11
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 01/17/2025