Socrates Sculpture Park Administration Building Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a new administration building at Socrates Sculpture Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: May 2016
Projected Completion Date: August 2017
Completion Date: August 2019

Procurement

Start Date: August 2019
Projected Completion Date: May 2020
Completion Date: June 2022

Construction

Start Date: August 2022
Projected Completion Date: February 2024
Completion Date: April 2024

Understand how we build parks.

Funding

Total Funding: $6,614,000
Funding Sources:
  • Borough President
  • City Council
  • Private

Location

Socrates Sculpture Park, Queens
Broadway, Vernon Boulevard, 31st Drive and Hallets Cove
Community Board: 01

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 11/22/2024