Waring Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the basketball courts and the playground at Waring Playground in Bronx Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2017
Projected Completion Date:
October 2018
Completion Date:
December 2018
Procurement
Start Date: December 2018
Projected Completion Date:
September 2019
Completion
Date:
May 2021
Construction
Start Date: July 2021
Projected Completion Date:
July 2022
Completion Date: March 2022
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
- Mayoral
- State
Location
Bronx Park, Bronx
Located at Waring Avenue and Bronx Park East.
Community Board: 06, 07, 11, 12
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project