Waring Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the basketball courts and the playground at Waring Playground in Bronx Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2017
Projected Completion Date: October 2018
Completion Date: December 2018

Procurement

Start Date: December 2018
Projected Completion Date: September 2019
Completion Date: May 2021

Construction

Start Date: July 2021
Projected Completion Date: July 2022
Completion Date: March 2022

Understand how we build parks.

Funding

Total Funding: $3,600,000
Funding Sources:
  • Borough President
  • City Council
  • Mayoral
  • State

Location

Bronx Park, Bronx
Located at Waring Avenue and Bronx Park East.
Community Board: 06, 07, 11, 12

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 01/17/2025