Sunset Park Pavement, Fencing, and Bench Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct paths, benches and fencing at Sunset Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: September 2015
Projected Completion Date:
June 2016
Completion Date:
July 2016
Procurement
Start Date: July 2016
Projected Completion Date:
April 2017
Completion
Date:
July 2017
Construction
Start Date: September 2017
Projected Completion Date:
September 2018
Completion Date: December 2018
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
Location
Sunset Park, Brooklyn
5th Avenue, 6th Avenue, 41st Street, 44th Street
Community Board: 07
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks