Roy Wilkins Park Track and Field Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the track and synthetic turf field in Roy Wilkins Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: January 2016
Projected Completion Date:
October 2016
Completion Date:
October 2016
Procurement
Start Date: October 2016
Projected Completion Date:
July 2017
Completion
Date:
October 2017
Construction
Start Date: November 2017
Projected Completion Date:
November 2018
Completion Date: November 2018
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
Location
Roy Wilkins Recreation Center, Queens
Merrick Boulevard between 116th Avenue and 118th Road
Community Board: 12
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 01/17/2025