Crowley Playground Reconstruction
-
100% complete
-
100% complete
-
48% complete
This project will reconstruct Crowley Playground.
Project Notes
Project Update: This project is in active construction.
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: January 2021
Projected Completion Date:
January 2022
Completion Date:
August 2022
Procurement
Start Date: August 2022
Projected Completion Date:
May 2023
Completion
Date:
July 2024
Construction
Start Date: August 2024
Projected Completion Date:
August 2025
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
Location
Crowley Playground, Queens
57th Avenue at 83rd Street
Community Board: 04
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 01/17/2025