Crowley Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    48% complete

This project will reconstruct Crowley Playground.

Project Notes

Project Update: This project is in active construction.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: January 2021
Projected Completion Date: January 2022
Completion Date: August 2022

Procurement

Start Date: August 2022
Projected Completion Date: May 2023
Completion Date: July 2024

Construction

Start Date: August 2024
Projected Completion Date: August 2025

Understand how we build parks.

Funding

Total Funding: $3,770,000
Funding Sources:
  • Borough President
  • City Council

Location

Crowley Playground, Queens
57th Avenue at 83rd Street
Community Board: 04

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 01/17/2025