Crowley Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    20% complete

This project will reconstruct Crowley Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: January 2021
Projected Completion Date: January 2022
Completion Date: August 2022

Procurement

Start Date: August 2022
Projected Completion Date: May 2023
Completion Date: July 2024

Construction

Start Date: August 2024
Projected Completion Date: August 2025

Understand how we build parks.

Funding

Total Funding: $3,770,000
Funding Sources:
  • Borough President
  • City Council

Location

Crowley Playground, Queens
57th Avenue at 83rd Street
Community Board: 04

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 10/11/2024