Kossuth Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Kossuth Playground in Mosholu Parkway to include new play equipment, spray shower features, basketball courts, fencing, pavement, benches, lighting and plantings.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2017
Projected Completion Date: October 2018
Completion Date: October 2018

Procurement

Start Date: October 2018
Projected Completion Date: July 2019
Completion Date: September 2019

Construction

Start Date: October 2019
Projected Completion Date: October 2020
Completion Date: October 2020

Understand how we build parks.

Funding

Total Funding: $3,356,000
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Location

Mosholu Parkway, Bronx
East Mosholu Parkway North between Kossuth Avenue and Steuben Avenue
Community Board: 07, 08

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 11/22/2024