Loreto Playground Asphalt Multi-Purpose Play Area Construction
-
100% complete
-
100% complete
-
100% complete
This project will construct an expanded asphalt multi-purpose play area in Loreto Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: February 2018
Projected Completion Date:
February 2019
Completion Date:
February 2019
Procurement
Start Date: February 2019
Projected Completion Date:
November 2019
Completion
Date:
November 2019
Construction
Start Date: September 2020
Projected Completion Date:
September 2021
Completion Date: August 2022
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- Mayoral
- State
Location
Loreto Playground, Bronx
Morris Park Avenue, Tomlinson Avenue, Haight Avenue, and Van Nest Avenue
Community Board: 11
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project
Last updated: 01/17/2025