Playground Thirty Five XXXV Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Playground Thirty Five XXXV.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: April 2016
Projected Completion Date: April 2017
Completion Date: May 2017

Procurement

Start Date: May 2017
Projected Completion Date: February 2018
Completion Date: April 2018

Construction

Start Date: May 2018
Projected Completion Date: May 2019
Completion Date: December 2019

Understand how we build parks.

Funding

Total Funding: $2,986,000
Funding Source: Mayoral

Location

Playground Thirty Five XXXV, Queens
35th Avenue between Steinway Street and 41st Street
Community Board: 01

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 11/22/2024