Sankofa Park Reconstruction
-
100% complete
-
100% complete
-
93% complete
This project will reconstruct the playground and construct an African Burial Ground commemorative area at Sankofa Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: June 2019
Projected Completion Date:
June 2021
Completion Date:
February 2022
Procurement
Start Date: February 2022
Projected Completion Date:
November 2022
Completion
Date:
July 2023
Construction
Start Date: November 2023
Projected Completion Date:
November 2024
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
- Mayoral
- State
Location
Sankofa Park, Brooklyn
Livonia Avenue between Barbey Street and Schenck Avenue
Community Board: 05
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 11/22/2024