Sankofa Park Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    93% complete

This project will reconstruct the playground and construct an African Burial Ground commemorative area at Sankofa Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: June 2019
Projected Completion Date: June 2021
Completion Date: February 2022

Procurement

Start Date: February 2022
Projected Completion Date: November 2022
Completion Date: July 2023

Construction

Start Date: November 2023
Projected Completion Date: November 2024

Understand how we build parks.

Funding

Total Funding: $4,875,000
Funding Sources:
  • Borough President
  • City Council
  • Mayoral
  • State

Location

Sankofa Park, Brooklyn
Livonia Avenue between Barbey Street and Schenck Avenue
Community Board: 05

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/22/2024