Hell Gate Pathway Construction Phase 3
-
100% complete
-
100% complete
-
100% complete
This project will construct a multi use pedestrian pathway under the Amtrak Viaduct at Wards Island Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: January 2016
Projected Completion Date:
January 2017
Completion Date:
May 2017
Procurement
Start Date: May 2017
Projected Completion Date:
February 2018
Completion
Date:
May 2018
Construction
Start Date: December 2018
Projected Completion Date:
May 2020
Completion Date: December 2019
Understand how we build parks.
Funding
Funding Sources:
- Federal
- Mayoral
- State
Location
Wards Island Park, Manhattan
Under the Amtrak Viaduct from Hell Gate Bridge to Column 27 and Central Road
Community Board: 11
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 01/17/2025