Hell Gate Pathway Construction Phase 3

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a multi use pedestrian pathway under the Amtrak Viaduct at Wards Island Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: January 2016
Projected Completion Date: January 2017
Completion Date: May 2017

Procurement

Start Date: May 2017
Projected Completion Date: February 2018
Completion Date: May 2018

Construction

Start Date: December 2018
Projected Completion Date: May 2020
Completion Date: December 2019

Understand how we build parks.

Funding

Total Funding: $4,000,000
Funding Sources:
  • Federal
  • Mayoral
  • State

Location

Wards Island Park, Manhattan
Under the Amtrak Viaduct from Hell Gate Bridge to Column 27 and Central Road
Community Board: 11

 

Project Staff

Project Liaison: Steve Simon