Flushing Meadows Corona Park Mauro Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Mauro Playground in Flushing Meadows Corona Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: May 2017
Projected Completion Date: May 2018
Completion Date: June 2018

Procurement

Start Date: June 2018
Projected Completion Date: March 2019
Completion Date: April 2019

Construction

Start Date: April 2019
Projected Completion Date: October 2020
Completion Date: November 2019

Understand how we build parks.

Funding

Total Funding: $4,786,000
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Location

Flushing Meadows Corona Park, Queens
Park Drive East at 73rd Terrace
Community Board: 03, 04, 06, 07, 08

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 11/22/2024