Broad Channel American Park Field Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    62% complete

This project will reconstruct the asphalt ballfield in Broad Channel American Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2020
Projected Completion Date: May 2022
Completion Date: November 2022

Procurement

Start Date: November 2022
Projected Completion Date: July 2023
Completion Date: June 2024

Construction

Start Date: August 2024
Projected Completion Date: August 2025

Understand how we build parks.

Funding

Total Funding: $3,000,000
Funding Source: City Council

Location

Broad Channel American Park, Queens
Cross Bay Boulevard and West 22nd Road
Community Board: 14

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 11/22/2024