Broad Channel American Park Field Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    92% complete

This project will reconstruct the asphalt ballfield in Broad Channel American Park.

Project Notes

Project Update: This project is in active construction.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2020
Projected Completion Date: May 2022
Completion Date: November 2022

Procurement

Start Date: November 2022
Projected Completion Date: July 2023
Completion Date: June 2024

Construction

Start Date: August 2024
Projected Completion Date: August 2025

Understand how we build parks.

Funding

Total Funding: $3,000,000
Funding Source: City Council

Location

Broad Channel American Park, Queens
Cross Bay Boulevard and West 22nd Road
Community Board: 14

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 01/17/2025