Broad Channel American Park Field Reconstruction
-
100% complete
-
100% complete
-
62% complete
This project will reconstruct the asphalt ballfield in Broad Channel American Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: November 2020
Projected Completion Date:
May 2022
Completion Date:
November 2022
Procurement
Start Date: November 2022
Projected Completion Date:
July 2023
Completion
Date:
June 2024
Construction
Start Date: August 2024
Projected Completion Date:
August 2025
Understand how we build parks.
Funding
Funding Source: City Council
Location
Broad Channel American Park, Queens
Cross Bay Boulevard and West 22nd Road
Community Board: 14
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks