Forest Park Glendale Entrance Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a new multi-use bicycle and pedestrian pathway into Forest Park from Myrtle Avenue, including streetscape and park pathway improvements.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: April 2017
Projected Completion Date: April 2018
Completion Date: July 2019

Procurement

Start Date: July 2019
Projected Completion Date: April 2020
Completion Date: August 2021

Construction

Start Date: September 2021
Projected Completion Date: September 2022
Completion Date: June 2022

Understand how we build parks.

Funding

Total Funding: $3,409,000
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Location

Forest Park, Queens
Forest Park Drive and Myrtle Avenue
Community Board: 05, 05, 06, 09

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 01/17/2025