Playground 62 Reconstruction
-
100% complete
-
100% complete
-
9% complete
This project will reconstruct Playground 62.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: November 2020
Projected Completion Date:
November 2021
Completion Date:
June 2022
Procurement
Start Date: June 2022
Projected Completion Date:
March 2023
Completion
Date:
July 2024
Construction
Start Date: August 2024
Projected Completion Date:
August 2025
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
Location
Playground Sixty Two LXII, Queens
Yellowstone Boulevard between 62nd Avenue and 62nd Road
Community Board: 06
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 11/22/2024