Playground 62 Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    9% complete

This project will reconstruct Playground 62.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2020
Projected Completion Date: November 2021
Completion Date: June 2022

Procurement

Start Date: June 2022
Projected Completion Date: March 2023
Completion Date: July 2024

Construction

Start Date: August 2024
Projected Completion Date: August 2025