Playground 62 Reconstruction
-
100% complete
-
100% complete
-
15% complete
This project will reconstruct Playground 62.
Project Notes
Project Update: This project is in active construction.
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: November 2020
Projected Completion Date:
November 2021
Completion Date:
June 2022
Procurement
Start Date: June 2022
Projected Completion Date:
March 2023
Completion
Date:
July 2024
Construction
Start Date: August 2024
Projected Completion Date:
August 2025
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
Location
Playground Sixty Two LXII, Queens
Yellowstone Boulevard between 62nd Avenue and 62nd Road
Community Board: 06
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 01/17/2025