Nautilus Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct Nautilus Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: January 2019
Projected Completion Date:
January 2020
Completion Date:
May 2020
Procurement
Start Date: May 2020
Projected Completion Date:
February 2021
Completion
Date:
April 2022
Construction
Start Date: August 2022
Projected Completion Date:
August 2023
Completion Date: August 2023
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
Location
Roy Wilkins Recreation Center, Queens
Merrick Boulevard and Baisley Boulevard
Community Board: 12
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 01/17/2025