Cunningham Park Lower Redwood Playground Tot Lot Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Lower Redwood Playground in Cunningham Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: June 2016
Projected Completion Date: June 2017
Completion Date: July 2017

Procurement

Start Date: July 2017
Projected Completion Date: April 2018
Completion Date: June 2018

Construction

Start Date: July 2018
Projected Completion Date: July 2019
Completion Date: April 2020

Understand how we build parks.

Funding

Total Funding: $1,837,000
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Location

Cunningham Park, Queens
193rd Street and Aberdeen Road
Community Board: 08

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 11/22/2024