Norelli-Hargreaves Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the play area, spray shower, and seating area at Norelli-Hargreaves Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: May 2016
Projected Completion Date:
June 2017
Completion Date:
August 2017
Procurement
Start Date: August 2017
Projected Completion Date:
May 2018
Completion
Date:
July 2018
Construction
Start Date: October 2018
Projected Completion Date:
September 2019
Completion Date: September 2019
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- Mayoral
Location
Norelli-Hargreaves Playground, Queens
Van Wyck Expressway, 142nd Street, 106th Avenue
Community Board: 12
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 01/17/2025