Rainey Park Playground, Picnic Grove and Basketball Court Reconstruction
-
100% complete
-
100% complete
-
95% complete
This project will reconstruct the playground, picnic grove and basketball court at Rainey Park.
Project Notes
Project Update: This project is in active construction.
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: May 2019
Projected Completion Date:
May 2020
Completion Date:
September 2021
Procurement
Start Date: September 2021
Projected Completion Date:
June 2022
Completion
Date:
July 2023
Construction
Start Date: September 2023
Projected Completion Date:
September 2024
Adjusted Completion Date: November 2024
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
- Mayoral
Location
Rainey Park, Queens
Vernon Boulevard between 34th Avenue and 33rd Road
Community Board: 01