Rainey Park Playground, Picnic Grove and Basketball Court Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    91% complete

This project will reconstruct the playground, picnic grove and basketball court at Rainey Park.

Project Notes

Due to COVID related impacts, this project may have experienced schedule delays.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: May 2019
Projected Completion Date: May 2020
Completion Date: September 2021

Procurement

Start Date: September 2021
Projected Completion Date: June 2022
Completion Date: July 2023

Construction

Start Date: September 2023
Projected Completion Date: September 2024
Adjusted Completion Date: November 2024

Understand how we build parks.

Funding

Total Funding: $8,511,000
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Location

Rainey Park, Queens
Vernon Boulevard between 34th Avenue and 33rd Road
Community Board: 01

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 10/11/2024