Newtown Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct paths and plantings on the upper lawn area of Newtown Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: June 2016
Projected Completion Date:
June 2017
Completion Date:
June 2017
Procurement
Start Date: June 2017
Projected Completion Date:
March 2018
Completion
Date:
July 2018
Construction
Start Date: September 2018
Projected Completion Date:
September 2019
Completion Date: September 2019