Hallets Cove Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Hallets Cove Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2016
Projected Completion Date: October 2017
Completion Date: November 2017

Procurement

Start Date: November 2017
Projected Completion Date: August 2018
Completion Date: November 2018

Construction

Start Date: February 2019
Projected Completion Date: February 2020
Completion Date: December 2019

Understand how we build parks.

Funding

Total Funding: $1,866,000
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Location

Hallets Cove Playground, Queens
Vernon Boulevard between Main Avenue and Astoria Boulevard
Community Board: 01

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 01/17/2025