Crocheron Park Little League Ballfields Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the ballfields at Crocheron Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: June 2017
Projected Completion Date:
June 2018
Completion Date:
June 2018
Procurement
Start Date: June 2018
Projected Completion Date:
March 2019
Completion
Date:
April 2019
Construction
Start Date: July 2019
Projected Completion Date:
July 2020
Completion Date: July 2020
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
Location
Crocheron Park, Queens
Between Cross Island Parkway, Corbett Road, and 214th Place
Community Board: 11
Project Staff
Project Liaison: Meira Berkower
Contact NYC Parks
about this project
Last updated: 01/17/2025