Sunset Park Adult Fitness Area Construction
-
100% complete
-
100% complete
-
100% complete
This project will construct an adult fitness area in Sunset Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: September 2015
Projected Completion Date:
November 2016
Completion Date:
December 2016
Procurement
Start Date: December 2016
Projected Completion Date:
September 2017
Completion
Date:
November 2017
Construction
Start Date: March 2018
Projected Completion Date:
March 2019
Completion Date: December 2018
Understand how we build parks.
Funding
Funding Source: City Council
Location
Sunset Park, Brooklyn
41st Street at 6th Avenue
Community Board: 07
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 01/17/2025