Sunset Park Adult Fitness Area Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct an adult fitness area in Sunset Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2015
Projected Completion Date: November 2016
Completion Date: December 2016

Procurement

Start Date: December 2016
Projected Completion Date: September 2017
Completion Date: November 2017

Construction

Start Date: March 2018
Projected Completion Date: March 2019
Completion Date: December 2018

Understand how we build parks.

Funding

Total Funding: $335,000
Funding Source: City Council

Location

Sunset Park, Brooklyn
41st Street at 6th Avenue
Community Board: 07

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 01/17/2025