Ennis Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Ennis Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: January 2016
Projected Completion Date: January 2017
Completion Date: June 2017

Procurement

Start Date: June 2017
Projected Completion Date: March 2018
Completion Date: May 2018

Construction

Start Date: July 2018
Projected Completion Date: July 2019
Completion Date: July 2019

Understand how we build parks.

Funding

Total Funding: $2,580,000
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Location

Ennis Playground, Brooklyn
11th Street, 12th Street, 2nd Avenue, 3rd Avenue
Community Board: 06

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/22/2024