Ennis Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct Ennis Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: January 2016
Projected Completion Date:
January 2017
Completion Date:
June 2017
Procurement
Start Date: June 2017
Projected Completion Date:
March 2018
Completion
Date:
May 2018
Construction
Start Date: July 2018
Projected Completion Date:
July 2019
Completion Date: July 2019
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
- Mayoral
Location
Ennis Playground, Brooklyn
11th Street, 12th Street, 2nd Avenue, 3rd Avenue
Community Board: 06
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 11/22/2024