Friends Field Playground Expansion
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct portions of the existing playground at Friends Field, including the removal of the existing safety surface, and the expansion of the existing playground area.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: September 2015
Projected Completion Date:
December 2016
Completion Date:
June 2017
Procurement
Start Date: June 2017
Projected Completion Date:
March 2018
Completion
Date:
June 2018
Construction
Start Date: September 2018
Projected Completion Date:
September 2019
Completion Date: December 2019
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
- Mayoral
Location
Friends Field, Brooklyn
Avenue L and East 4th Street
Community Board: 12
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 01/17/2025