Asser Levy Park Playground & Path Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the playground and adjacent paths in Asser Levy Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2015
Projected Completion Date: September 2016
Completion Date: February 2017

Procurement

Start Date: February 2017
Projected Completion Date: October 2017
Completion Date: September 2017

Construction

Start Date: October 2017
Projected Completion Date: October 2018
Completion Date: December 2018

Understand how we build parks.

Funding

Total Funding: $3,850,000
Funding Sources:
  • City Council
  • Mayoral

Location

Asser Levy Park, Brooklyn
West 5th Street between Surf Avenue and Sea Breeze Avenue
Community Board: 13

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 01/17/2025