Asser Levy Park Playground & Path Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the playground and adjacent paths in Asser Levy Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: September 2015
Projected Completion Date:
September 2016
Completion Date:
February 2017
Procurement
Start Date: February 2017
Projected Completion Date:
October 2017
Completion
Date:
September 2017
Construction
Start Date: October 2017
Projected Completion Date:
October 2018
Completion Date: December 2018
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Location
Asser Levy Park, Brooklyn
West 5th Street between Surf Avenue and Sea Breeze Avenue
Community Board: 13
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 01/17/2025