Dyker Beach Park Synthetic Turf Soccer Field Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the existing synthetic turf soccer field, bleachers, and drinking fountain at Dyker Beach Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: February 2016
Projected Completion Date: August 2016
Completion Date: September 2016

Procurement

Start Date: September 2016
Projected Completion Date: June 2017
Completion Date: July 2017

Construction

Start Date: September 2017
Projected Completion Date: September 2018
Completion Date: June 2018

Understand how we build parks.

Funding

Total Funding: $1,697,000
Funding Source: City Council

Location

Dyker Beach Park, Brooklyn
14th Avenue between Benson Avenue and Bath Avenue
Community Board: 10

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project