Bronx and Queens Reforestation FY16
-
100% complete
-
100% complete
-
100% complete
This project will remove invasive trees, shrubs, plants and vines; excavate and clear sites; remove tree stumps; prepare tree pits; furnish, plant, maintain and replace trees; install native seed mixes; and install osprey nests in the Bronx and Queens.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: July 2015
Projected Completion Date:
September 2015
Completion Date:
November 2015
Procurement
Start Date: November 2015
Projected Completion Date:
August 2016
Completion
Date:
July 2016
Construction
Start Date: July 2016
Projected Completion Date:
January 2019
Completion Date: January 2019
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Location
Various locations in the Bronx and Queens