Staten Island Greenbelt Recreation Center Parking Area Expansion

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will expand the parking area at Greenbelt Recreation Center.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: December 2015
Projected Completion Date: January 2017
Completion Date: February 2017

Procurement

Start Date: February 2017
Projected Completion Date: November 2017
Completion Date: March 2018

Construction

Start Date: May 2018
Projected Completion Date: May 2019
Completion Date: April 2019

Understand how we build parks.

Funding

Total Funding: $1,158,000
Funding Sources:
  • City Council
  • Mayoral

Location

Blood Root Valley, Staten Island
West of Brielle Avenue between Rockland and Walcott Avenues.
Community Board: 02

 

Project Staff

Project Liaison: Joseph Homsey