Sorrentino Recreation Center Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct portions of Sorrentino Recreation Center.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: July 2015
Projected Completion Date:
September 2015
Completion Date:
December 2016
Procurement
Start Date: December 2016
Projected Completion Date:
September 2017
Completion
Date:
January 2018
Construction
Start Date: March 2018
Projected Completion Date:
March 2019
Completion Date: March 2019
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Sorrentino Recreation Center, Queens
18-48 Cornaga Avenue
Community Board: 14
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks
about this project