St. Mary's Recreation Center Pool and Gymnasium HVAC Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will provide a heating, ventilation, air conditioning, and dehumidification system to serve the swimming pool and gymnasium at St. Mary's Recreation Center, as well as ventilation upgrades throughout the building.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: May 2015
Projected Completion Date: September 2016
Completion Date: October 2016

Procurement

Start Date: October 2016
Projected Completion Date: July 2017
Completion Date: October 2017

Construction

Start Date: December 2017
Projected Completion Date: December 2018
Completion Date: December 2018

Understand how we build parks.

Funding

Total Funding: $2,147,000
Funding Source: Mayoral