St. Mary's Playground Multi-Purpose Area Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the existing multipurpose play area at St. Mary's Playground to include a skate park, basketball courts, multi-use synthetic turf field, adult fitness equipment and color seal coat walking track.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: February 2015
Projected Completion Date: June 2016
Completion Date: July 2016

Procurement

Start Date: July 2016
Projected Completion Date: April 2017
Completion Date: July 2017

Construction

Start Date: October 2017
Projected Completion Date: October 2018
Completion Date: July 2019

Understand how we build parks.

Funding

Total Funding: $860,000
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Location

St. Mary's Park, Brooklyn
Smith Street between Nelson Street and Luquer Street
Community Board: 06

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project