St. Mary's Playground Multi-Purpose Area Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the existing multipurpose play area at St. Mary's Playground to include a skate park, basketball courts, multi-use synthetic turf field, adult fitness equipment and color seal coat walking track.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: February 2015
Projected Completion Date:
June 2016
Completion Date:
July 2016
Procurement
Start Date: July 2016
Projected Completion Date:
April 2017
Completion
Date:
July 2017
Construction
Start Date: October 2017
Projected Completion Date:
October 2018
Completion Date: July 2019
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
- Mayoral
Location
St. Mary's Park, Brooklyn
Smith Street between Nelson Street and Luquer Street
Community Board: 06
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project