Lt. Joseph Petrosino Park Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Lt. Joseph Petrosino Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: April 2016
Projected Completion Date: April 2017
Completion Date: May 2017

Procurement

Start Date: May 2017
Projected Completion Date: January 2018
Completion Date: November 2017

Construction

Start Date: January 2018
Projected Completion Date: April 2019
Completion Date: January 2019

Understand how we build parks.

Funding

Total Funding: $4,018,000
Funding Source: Mayoral

Location

Lt. Joseph Petrosino Park, Brooklyn
70th Street, 16th Avenue, 71st Street, New Utrecht Avenue
Community Board: 11

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/22/2024