Epiphany Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the playground, spray shower, seating, handball and basketball courts, perimeter fence, and security lighting at Epiphany Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: March 2016
Projected Completion Date:
March 2017
Completion Date:
October 2020
Procurement
Start Date: October 2020
Projected Completion Date:
July 2021
Completion
Date:
July 2022
Construction
Start Date: August 2022
Projected Completion Date:
August 2023
Completion Date: March 2024
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Epiphany Playground, Brooklyn
Berry Street between South 9th Street and South 10th Street
Community Board: 01
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 01/17/2025