Epiphany Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the playground, spray shower, seating, handball and basketball courts, perimeter fence, and security lighting at Epiphany Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2016
Projected Completion Date: March 2017
Completion Date: October 2020

Procurement

Start Date: October 2020
Projected Completion Date: July 2021
Completion Date: July 2022

Construction

Start Date: August 2022
Projected Completion Date: August 2023
Completion Date: March 2024

Understand how we build parks.

Funding

Total Funding: $3,575,000
Funding Source: Mayoral

Location

Epiphany Playground, Brooklyn
Berry Street between South 9th Street and South 10th Street
Community Board: 01

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 01/17/2025