Rev. Dr. Maggie Howard Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the playground, multi-use fields, basketball and handball courts, and water features at Rev. Dr. Maggie Howard Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2016
Projected Completion Date: August 2017
Completion Date: December 2017

Procurement

Start Date: December 2017
Projected Completion Date: September 2018
Completion Date: August 2018

Construction

Start Date: September 2018
Projected Completion Date: March 2020
Completion Date: April 2021

Understand how we build parks.

Funding

Total Funding: $10,034,000
Funding Source: Mayoral

Location

Rev. Dr. Maggie Howard Playground, Staten Island
Tompkins Avenue between Broad Street and Hill Street
Community Board: 01

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 01/17/2025