Carlton Park Landscape and Ida Court Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the play areas, paths, fencing, landscape and park amenities at Carlton Park and Ida Court Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: January 2016
Projected Completion Date:
May 2017
Completion Date:
May 2017
Procurement
Start Date: May 2017
Projected Completion Date:
February 2018
Completion
Date:
December 2017
Construction
Start Date: March 2018
Projected Completion Date:
September 2019
Completion Date: September 2019
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
- Mayoral
Locations
-
Harris Brothers Park, Staten Island
Foster Road & Carlton Avenue
Community Board: 03 -
Ida Court, Staten Island
Drumgoole Road East, Ida Court, North Railroad Street
Community Board: 03
Project Staff
Project Liaison: Joseph Homsey
Contact NYC Parks
about this project
Last updated: 11/22/2024