Bloomingdale Park Synthetic Turf Field Construction
-
100% complete
-
100% complete
-
100% complete
This project will construct a new synthetic turf multi-use field and reconstruct the existing synthetic turf soccer field at Bloomingdale Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: January 2016
Projected Completion Date:
March 2017
Completion Date:
September 2017
Procurement
Start Date: September 2017
Projected Completion Date:
June 2018
Completion
Date:
April 2019
Construction
Start Date: June 2019
Projected Completion Date:
November 2020
Completion Date: November 2020
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
Location
Bloomingdale Park, Staten Island
Lenevar Avenue between Drumgoole Road West and Ramona Avenue
Community Board: 03
Project Staff
Project Liaison: Joseph Homsey
Contact NYC Parks
about this project