Bloomingdale Park Synthetic Turf Field Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a new synthetic turf multi-use field and reconstruct the existing synthetic turf soccer field at Bloomingdale Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: January 2016
Projected Completion Date: March 2017
Completion Date: September 2017

Procurement

Start Date: September 2017
Projected Completion Date: June 2018
Completion Date: April 2019

Construction

Start Date: June 2019
Projected Completion Date: November 2020
Completion Date: November 2020

Understand how we build parks.

Funding

Total Funding: $4,050,000
Funding Sources:
  • Borough President
  • City Council

Location

Bloomingdale Park, Staten Island
Lenevar Avenue between Drumgoole Road West and Ramona Avenue
Community Board: 03

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project