Red Hook Recreation Area Ballfields 5-8 Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will convert four ballfields from natural turf to synthetic turf and remediate soils at Red Hook Recreation Area.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2015
Projected Completion Date: December 2016
Completion Date: June 2017

Procurement

Start Date: June 2017
Projected Completion Date: March 2018
Completion Date: May 2018

Construction

Start Date: September 2018
Projected Completion Date: March 2020
Completion Date: December 2021

Understand how we build parks.

Funding

Total Funding: $17,391,000
Funding Source: Mayoral

Location

Red Hook Recreation Area, Brooklyn
Lorraine Street, Bay Street, Hicks Street and Henry Street
Community Board: 06

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 01/17/2025