Manhattan Street Tree Planting FY16

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will plant new trees in Manhattan.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2015
Projected Completion Date: May 2015
Completion Date: May 2015

Procurement

Start Date: May 2015
Projected Completion Date: February 2016
Completion Date: February 2016

Construction

Start Date: February 2016
Projected Completion Date: August 2017
Completion Date: June 2017

Understand how we build parks.

Funding

Total Funding: $1,566,000
Funding Sources:
  • Mayoral
  • Private

Location

Various locations, Manhattan

Project Staff

Contact NYC Parks about this project

Last updated: 10/11/2024